Texas Data Centers Face Tax Policy Scrutiny and New Permitting Limits

by Will Ramirez, on Nov 16, 2026, 7:00:00 AM

Texas is an important location for data center investment, and for more than a decade the state has supported that growth in part through sales tax exemptions on the equipment and electricity these facilities use. In 2026, two things changed at once. State leaders began debating whether those exemptions should continue, and state agencies started adding new review requirements for data center projects.

For any company planning a Texas data center, tax eligibility is now only part of the picture. Permitting and power access have become just as central to whether and when a project can proceed.

Recent Program Activity: The Tax Exemptions

Texas offers two sales tax exemptions for data centers, and both remain in law. Under Tax Code 151.359, created in 2013, a qualifying data center of at least 100,000 square feet that invests at least $200 million within five years of Comptroller certification and creates at least 20 qualifying jobs is exempt from the state sales and use tax on specified qualifying purchases, including equipment and electricity, for 10 years, or for 15 years if the investment reaches at least $250 million within that five year period. Qualifying jobs are permanent and full time and must meet a 120 percent county average weekly wage test.

Under Tax Code 151.3595, added in 2015, a qualifying large data center project is exempt for 20 years. It requires at least 250,000 square feet, at least $500 million invested over five years from certification, at least 40 qualifying jobs, and a contract for at least 20 megawatts of transmission capacity. Unlike the regular exemption, which applies only to state tax, the large project exemption also covers local sales tax on qualifying purchases. Both programs include Comptroller oversight, with a five year audit, annual job review, and revocation if a project fails to meet the requirements.

At its July 27 hearing, the Senate Finance Committee examined the costs and consequences of these data center sales tax exemptions and potential safeguards for Texans.

A New Permitting Posture

The bigger change in 2026 came through a series of executive directives. On June 10, the Governor directed the Public Utility Commission and ERCOT to ensure that data center interconnections do not raise residential bills and that data centers pay for the electric infrastructure needed to serve them. On August 3, he directed the Public Utility Commission and ERCOT to audit all data centers moving through ERCOT’s interconnection process. On September 14, he directed the Texas Water Development Board to enforce water use reporting. Then, on September 21, he directed the Texas Commission on Environmental Quality to halt the permits sought by data centers until the ERCOT audit is complete.

As of November 4, TCEQ’s public notice states that STEERS is temporarily shut down while the agency modifies its application review process under the September 21 directive, with that work anticipated to finish in mid November. ERCOT’s data center information request, directed at developers of data centers of at least 25 megawatts pursuing interconnection, had an October 12 response deadline and anticipates publication of a report on or before December 10. Neither date should be treated as a guaranteed resumption date for data center permitting. Companies should confirm the status of their specific approvals with the relevant agency.

The SB 6 Power Rules

Separately, Senate Bill 6, enacted in 2025, directs the Public Utility Commission to establish interconnection standards for qualifying large loads in ERCOT. The interconnection provisions apply to new or expanded service at a single site above the Public Utility Commission threshold, set at 75 megawatts unless the Commission determines a lower threshold is needed. The law’s December 31, 2026 deadline specifically addresses the rules that assign wholesale transmission costs, not every rule under the law.

Why It Matters

For data center developers, Texas has long combined available power, land, and a sales tax holiday into an attractive package. The exemptions remain available today, but tax eligibility does not establish that a project can obtain permits or interconnect on its planned schedule, and that gap is now the central planning issue.

Governor-elect Gina Hinojosa takes office in January 2027. During the campaign, she called for a pause on new data center approvals until lawmakers enact protections and advocated ending tax breaks for large data centers. Governor Abbott had also called for lawmakers to eliminate data center incentives. The November 3 election did not change either sales tax exemption or lift the September permitting directive. Developers should model qualifying purchases under current law and track any proposed legislation for its effective date and treatment of existing certifications. The current pause and audit are proceeding under the outgoing administration, and the ERCOT report is targeted before the January transition, so whether the pause continues into 2027 is not established. The effect of the SB 6 rules will depend on the final rules, the site, and the interconnection arrangements, so impacts will vary by project.

What Companies Should Do

Companies weighing a Texas data center should treat permitting and power access as gating items alongside incentives. That means confirming current permitting status with the relevant agency, understanding where a project sits in the ERCOT interconnection and audit process, and planning for the SB 6 requirements that apply to the site.

On the tax side, companies should model the project under current law while recognizing that the exemptions are under review, and track both the 2027 session and the agency audits as they conclude.

How SSG Can Help

Site Selection Group helps companies evaluate state and local incentives as part of location decisions, and we track developments like the Texas data center exemptions and the new permitting posture. We model incentive value against total project economics and help clients compare Texas against competing states.

If your company is planning a data center or other large project in Texas, contact SSG to assess how the current incentives, permitting status, and power rules affect your location strategy.

Program details verified against primary sources as of November 4, 2026. Program rules, application status, and administrative guidance can change; confirm current details with the administering agency before acting. This article is provided for general information and does not constitute tax or legal advice.